Gujarat
|
|
|
---|---|---|
Metering arrangement | Net and gross metering | |
Eligibility | All consumers | |
System size limit | Net metering: 1 kW – 1 MW; gross metering: 10 kW - 1 MW | |
Grid penetration (%) | 100% of rated DT capacity | |
Banking | Allowed; within monthly billing cycle | |
Tariff for surplus power | 65% and 75% of average tariff discovered in state auctions for REC projects and other projects respectively | |
Incentives | Transmission charges & losses, wheeling charges & losses | |
Cap on energy generation | NA | |
Others | CSS and AS applicable on systems failing to prove captive status |
|
Date of issue | 21-06-2016 |
Please provide the following details